Mount Hays wind farm pushed back one year

Activity on Mount Hays this summer will be quieter than initially thought as Katabatic Power, the proponents of the Prince Rupert’s Mount Hays Wind Farm, have had to push the time line of the project back significantly.

“Things on the project are going OK. We had to amend our agreement with B.C. Hydro to put the wind farm into service in 2009 and not in 2008 as we first thought. The challenge was in securing turbines for 2008, and we are working on a deal to get the turbines delivered for 2009,â€